Removal of LNAPL in Fracture Rock Aquifer, Campinas
Brief
At an active gasoline retail station in the state of Sao Paulo, Campinas, historical spills of diesel fuel resulted in the accumulation of light non aqueous phase liquids, (LNAPL) on the shallow groundwater. Based on API estimates, approximately 430 litres of recoverable LNAPL was present. ASR was retained by the facility’s owner to extract the LNAPL from the fractured rock. ASR's design and approach minimized the footprint of the system and energy requirements while considering noise issues for surrounding neighbours.
Process
The site owner along with their environmental consultant worked with ASR to develop a remedial work plan based on meeting the remedial objective of recovering as much of the LNAPL as technically feasible. After reviewing the geology, hydrogeology and geochemistry of the site, ASR developed a plan that used dual phase extraction (DPE) to recover the LNAPL. The DPE system recovered over 93% of the estimated LNAPL by lowering the water table and thus increasing the hydraulic gradient towards that extraction wells. The two phases were extracted using two pumps dedicated to the extraction of the groundwater and LNAPL, respectively. The liquid phases were treated with gravity separation, organoclay and activated carbon whereas the air phase was treated using catalytic oxidization.
Results
Over 389 litres of LNAPL recovered in the NAPL and water phases
Reduction of BTEX concentrations within the groundwater of greater than 81 percent
Reduction of diesel range concentrations greater than 51 percent
View More DetailsReady to get started?
Speak with our engineering team about how our environmental remediation services can help you in your remediation journey and take the next steps to building a better environment and a cleaner community with your project.
I'm ready to Start